TranBC:
Completed new bridge with old bridge removed - Oct. 29 - Day 100
TranBC:
Decommissioning of the old bridge - Oct. 28 - Day 99
TranBC:
Roadside barrier for safety along Georgetown Lake - Oct. 28 - Day 99
TranBC:
Parking line paint at ferry dock complete - Oct. 26 - Day 97
TranBC:
Centre line road paint complete - Oct. 26 - Day 97
TranBC:
Roadside barrier being installed - Oct. 24 - Day 95
TranBC:
South end approach to the bridge is complete - Oct. 24 - Day 95
TranBC:
Final leg of the community roads paving - Oct. 12 - Day 86
TranBC:
Removing materials from the south end of the bridge site for new approach - Oct. 12 - Day 86
TranBC:
Blasting at the south end of the bridge site, preparing for new approach - Oct. 11 - Day 85
TranBC:
Roadside barriers awaiting installation - Oct. 08 - Day 84
TranBC:
New Bridge -- October 08 --Day 84
TranBC:
New bridge and alignment, showing better sight lines -- Oct. 6 -- Day 82
TranBC:
Paving complete for west approach of new bridge -- Oct. 4 -- Day 80
TranBC:
Completing paving for west approach to new bridge -- Oct. 4 -- Day 80
TranBC:
Fresh asphalt on Lax Kw’alaams community roads -- Oct. 1 -- Day 78
TranBC:
Fresh paving in Lax Kw'alaams -- Oct. 1 -- Day 78
TranBC:
Laying gravel at site of new salt shed -- Oct. 1 -- Day 78
TranBC:
Pouring concrete on the new bridge -- Oct. 1 -- Day 78
TranBC:
September 29, 2016 - Day 76. Work continues on paving of the community streets in Lax Kw’alaams
TranBC:
September 29, 2016 - Day 76. Work continues on paving of the community streets in Lax Kw’alaams
TranBC:
September 29, 2016 Day 76. Work continues on paving of the community streets in Lax Kw’alaams
TranBC:
September 29, 2016 - Day 76. Material placement almost finished for bridge approaches
TranBC:
September 27, 2016 Day 74. Material being built up at the approaches to the new bridge
TranBC:
Bridge deck installed and ready for paving - Sept. 22 - Day 70
TranBC:
Bridge deck being installed - Sept. 22 - Day 70
TranBC:
Paving nearly complete at ferry dock - Sept. 22 - Day 70
TranBC:
Contractor paving roads of Lax Kw’alaams Sept. 22 - Day 70
TranBC:
Completed paving - Sept. 20 - Day 68
TranBC:
Crews nearing the end of paving work - Sept. 20 - Day 68