Mstreeman: 0001 The City
Mstreeman: 0002 Bottom up
Mstreeman: 0003 Top down
Mstreeman: 0004 Starting infrastructure
Mstreeman: 0005 front driveway
Mstreeman: 0006 Water Tap
Mstreeman: 0007 completing infrastructure 11600
Mstreeman: 0008 Starting the basement 0
Mstreeman: 0009 A dug basement
Mstreeman: 0010 Base rock for foundation
Mstreeman: 0011 Rock spread and retaining walls dug
Mstreeman: 0012 Wall foundations poured and forms going up
Mstreeman: 0013 Walls poured and braced
Mstreeman: 0014 Retaining Walls
Mstreeman: 0015 Concrete-a-sourus took a poop
Mstreeman: 0016 Nik talking to the builder
Mstreeman: 0017 The new basement walls
Mstreeman: 0018 Wood burning stove flu outlet
Mstreeman: 0019 Wood burning stove chimney
Mstreeman: 0020 plumbing drain
Mstreeman: 0021 Future Front Yard and Duck Elect going in
Mstreeman: 0022 Poured basement floor 37750
Mstreeman: 0023 House Building Materials
Mstreeman: 0024 1st floor installed over basement
Mstreeman: 0025 Cutting flooring to fit
Mstreeman: 0026 Garage
Mstreeman: 0027 Front Wall
Mstreeman: 0028 Garage Wall
Mstreeman: 0029 Framing Crew After rain day
Mstreeman: 0030 Nik inspecting floor trusses