Progress at East Gwillimbury GO Bus Facility | Avancées des travaux à l’installation d’autobus GO d’East Gwillimbury by Metrolinx
Photos
Albums
|
Groups
Favourites
|
Subscriptions
Contacts
|
Recommendations
Do you miss your pictures? Click here.
Do you have a flickr account?
Sign in!
©
Metrolinx
:
©
Metrolinx
:
Almost there.
©
Metrolinx
:
Exterior work at the main entrance.
©
Metrolinx
:
Outside work begins again.
©
Metrolinx
:
Building exterior.
©
Metrolinx
:
Exterior window wall system work in progress.
©
Metrolinx
:
From the inside - the window panels at the front of the facility.
©
Metrolinx
:
The interior work continues.
©
Metrolinx
:
The interior work begins at East Gwillimbury GO Bus Facility.
©
Metrolinx
:
Building precast concrete panels being installed.
©
Metrolinx
:
A view from up top, at the East Gwillimbury GO Bus Facility.
©
Metrolinx
:
Installing the roof deck at East Gwillimbury GO Bus Facility.
©
Metrolinx
:
Cranes continue to install the roof at the East Gwillimbury GO Bus Facility.
©
Metrolinx
:
Work progresses at East Gwillimbury with half the roof installed.
©
Metrolinx
:
©
Metrolinx
:
Structural Steel erection for roof deck at the new East Gwillimbury GO Bus Facility.
©
Metrolinx
:
Formwork Erection for the wall of the new East Gwillimbury GO Bus Facility.
©
Metrolinx
:
Concrete pour for the foundation.
©
Metrolinx
:
Laying reinforcement for the foundation at the future site of the East Gwillimbury GO Bus Facility.
©
Metrolinx
:
Trenches for foundations at the future site of the East Gwillimbury GO Bus Facility.