Metrolinx: One of the new signal masts which will be installed as part of the temporary track detour.
Metrolinx: Preliminary railway tie alignment for the track detour.
Metrolinx: Stockpiled rails to be be used to build the track detour.
Metrolinx: Installation of rails and railway ties.
Metrolinx: Installation of rails and railway ties.
Metrolinx: 1. Installation of one of the new signal masts next to the path of the future track detour.
Metrolinx: Thermite welding of the north detour track.
Metrolinx: Installation of a temporary crossing at South Blair Street.
Metrolinx: Looking east at the new south detour track and track surfacing equipment.
Metrolinx: Looking west at the site of the future underpass, between the CN tracks on the left and the recently shifted GO tracks on the right.
Metrolinx: Prep for track shift at Whitby's South Blair St.; new underpass will bring improved safety & efficient train movements.
Metrolinx: Train speeds had to be reduced between Whitby & Oshawa during prep work for track shift.
Metrolinx: Working all weekend on Whitby's South Blair Street track shift for future underpass.
Metrolinx: Working all weekend on Whitby's South Blair Street track shift.
Metrolinx: Working all weekend on Whitby's South Blair Street track shift; cutting tracks.
Metrolinx: Prep for track shift at the South Blair Street crossing; lifting track to install ballast underneath.
Metrolinx: Standing on the future site of the underpass; recently we shifted the GO tracks away from the CN tracks to allow for construction.
Metrolinx: 4. Building up of the subgrade for the new access road; looking east.
Metrolinx: 9. Construction of a shoring wall on the south side of the GO detour tracks.
Metrolinx: 8. Construction of a shoring wall on the south side of the GO detour tracks.
Metrolinx: 5. Future access road; looking east.
Metrolinx: 11. Grading and erosion control around the habitat compensation area.
Metrolinx: 10. Habitat compensation area between the East Rail Maintenance Facility and the South Blair St underpass sites.
Metrolinx: 1. Dewatering and removal of rubble at the future site of the new access road.
Metrolinx: Welding crews are welding ‘whalers’ to the piles. The ‘whalers’ are horizontal beams that hold the piles together.
Metrolinx: An overview of the excavation site for the shoring wall for the future rail-over-road underpass at the South Blair Street level crossing in Whitby. The underpass will improve pedestrian, rail and vehicular traffic flow in the area.
Metrolinx: Drilling under the CN Kingston subdivision to install horizontal tiebacks (steel rods that hold the together piles on each side) that prevent the shoring wall from sagging under the weight of the retained soil.
Metrolinx: 1. Rebar and formwork for the west abutment footing in the foreground, pier columns for the median lane of the future underpass at centre and a concrete pump in the background, pouring concrete into the formwork for the east abutment wall.
Metrolinx: 5. Concrete pump used to pour concrete into the formwork for the future east abutment wall.
Metrolinx: 6. The concrete pour into the east abutment wall continues as a VIA train speeds by in the background.