Marcus Wong from Geelong:
Excavators at work breaking up basalt from the future hospital basement
Marcus Wong from Geelong:
Bike lanes along Geelong Road taken over for the construction layover area
Marcus Wong from Geelong:
Multi-storey site offices along Ballarat Road
Marcus Wong from Geelong:
Looking into the new Footscray Hospital construction site from Tiernan Street
Marcus Wong from Geelong:
Concrete boom pumps at work on the base slab
Marcus Wong from Geelong:
Base slab poured at the new Footscray Hospital
Marcus Wong from Geelong:
Fence around the new Footscray Hospital construction site on Federal Street
Marcus Wong from Geelong:
Peeking under the fence into the new Footscray Hospital construction site from Federal Street
Marcus Wong from Geelong:
Tip trucks being loaded with soil from the eastern end of the hospital site
Marcus Wong from Geelong:
Excavator at work removing basalt from the future hospital basement
Marcus Wong from Geelong:
Excavator at work breaking up basalt from the future hospital basement
Marcus Wong from Geelong:
Mobile concrete boom pump pouring a foundation slab for a tower crane
Marcus Wong from Geelong:
Mobile concrete boom pump pouring a foundation slab for a tower crane
Marcus Wong from Geelong:
Excavators at work breaking up basalt from the future hospital basement
Marcus Wong from Geelong:
Looking over the bluestone wall to the townhouses of Edgewater and the new Footscray Hospital site
Marcus Wong from Geelong:
Looking down Geelong Road to the tower cranes of the New Footscray Hospital construction site
Marcus Wong from Geelong:
Looking over Edgewater towards the New Footscray Hospital construction site
Marcus Wong from Geelong:
Tower cranes at the New Footscray Hospital construction site loom over the houses along Droop Street, Footscray
Marcus Wong from Geelong:
Tower cranes at the New Footscray Hospital construction site loom over the houses along Droop Street, Footscray